SR EN 12699:2004

Execution of special geotechnical work - Displacement piles

1.1 This standard establishes general principles for the execution of displacement piles which are installes in the ground without excavation or removal of material from the ground except for limiting heave, vibration, removal of obstructions or to assist penetration. Piles are driven into the ground using impact, vibration, pressing, screwing or a combination of these methods. The material of displacement piles covered by this standard can be: -steel, -cast iron, -concrete, -timber, -grout, -combination of above.

43.43

Status : Withdrawn
Approval date : 7/28/2004
Publish date : 7/29/2004
Withdrawal date : 9/30/2015
Number of pages : 50
ICS : 93.020 Earthworks. Excavations. Foundation construction. Underground works
Technical Committee : 361 - Geotechnic

Relations with other standards: